IHC ConstructionSep 41 min readDSN-19 - Start of work 08/27/2024IHC has begun work at DSN-19 on 08/27/2024. Work is planned to be done within one month.Work includes, raising structure concrete shafts for access, installing structural steel and grating, regrading area to new elevation.
IHC has begun work at DSN-19 on 08/27/2024. Work is planned to be done within one month.Work includes, raising structure concrete shafts for access, installing structural steel and grating, regrading area to new elevation.
CS-10 under Wolf RD - Completion of work.On 08/16/2024 all work at the location was completed and road was reopened.
CS-10 Des Plaines Intersection of Rand and Wolf RoadsDue to heavy rain, flow in the structure, delayed our scheduled completion of the work planned for 07/31/2024. Current completion with...