CS-10 Des Plaines Intersection of Rand and Wolf RoadsIHC ConstructionJul 23, 20241 min readDue to heavy rain, flow in the structure, delayed our scheduled completion of the work planned for 07/31/2024.Current completion with traffic control removal is scheduled for 08/09/2024.
Due to heavy rain, flow in the structure, delayed our scheduled completion of the work planned for 07/31/2024.Current completion with traffic control removal is scheduled for 08/09/2024.
CS-10 under Wolf RD - Completion of work.On 08/16/2024 all work at the location was completed and road was reopened.