DSN-19 - Start of work 08/27/2024
IHC has begun work at DSN-19 on 08/27/2024. Work is planned to be done within one month. Work includes, raising structure concrete shafts...
DSN-19 - Start of work 08/27/2024
DS-8 - Start of work 08/06/2024
CS-10 under Wolf RD - Completion of work.
CS-10 Des Plaines Intersection of Rand and Wolf Roads
CS-10 Des Plaines Intersection of Rand and Wolf Roads
Start of Work - Des Plaines Structure CS-10 under Wolf/Rand intersection.
Mount Prospect-Completion of work inside Structure UDP 11A
Start of work-Mount Prospect-Work Inside Structure UDP 11A
Mount Prospect - Work Inside Structure UDP 11A